Significant progress has been made across the project, with key structural and civil works advancing across multiple areas.
At the multipurpose facility, structural steel erection has commenced, alongside electrical conduit extension for oval lighting. Concrete works for the access ramp are now underway, and foundation works have also started.
At the tennis courts, subbase proof rolling and soft spot rectification works have been completed.
In the carpark area, stormwater pipes and pits are nearing completion. Subbase works will continue following the replacement of some damaged electrical pits within the carpark.